2016 – New Road & Sewer Project
We completed a new road and sewer project doing drainage up to 4metres deep building traditional man holes installing gullies and connecting them, 500metres of kerbing, new ducting for services and trimming road stone ready for tarmac for Breheny Civil Engineering.
2018 – Radcliffe-on-Trent Junction Improvements
Radcliffe-on-Trent junction improvement scheme for Carnell group road widening, new kerbs , new drainage new footpaths on nights towing lighting towers out with our vans and working through the night under lane closures to meet deadlines for road to be tarmacked.
2020 – Chownsmill Roundabout for Carnell Group
Chownsmill round about for the Carnell group which we are still supplying labour for now has been a mixture of days and nights with 12 of our staff working on drainage , kerbing, footpaths, ducting and road formation meeting deadlines for traffic switched and working a pattern of 12 days on 2 days to help the client hit their targets.